In May 2012 we published an initial timeline published in May 2012 when the process began, as set out below.

In March 2013 we announced to staff that the latest expected timings were:

  • September 2013 for transfer to new catering provider
  • October 2013 for transfer to new facilities management provider

We are currently (May 2013) in the competitive dialogue phase in relation to facilities mananagement and catering.

We will be announcing the preferred providers in the summer that and undertaking TUPE information and consultation processes.

 

INITIAL EXPECTED TIMELINE - TFM (as announced in May 2012)

 

Early May 12

 

Publish OJEU notice & inform trade unions and affected staff

 

Communication  period

 

 

 

 

 

 

 

Early July 12

 

Pre-Qualification Questionnaire stage (PQQ)

 

Late July 12

 

Invite shortlist & competitive dialogue stage.  NB competitve dialogue stage continues until March 2013

 

Early March 13

 

Receive written tenders

 

 

 

Early April 13

 

Appoint preferred bidder

 

TUPE information &consultation period

 

Early May 13

 

Award contract

 

 

Early July 13

 

Start transition to new arrangements

 

Late Aug 13

 

New services fully operational

 

 

 

INITIAL EXPECTED TIMELINE – CATERING OPERATIONS (as announced in May 2012)

 

Early May 12

 

Publish OJEU notice & inform trade unions and affected staff

 

Communication  period

 

 

 

 

 

Early July 12

 

Pre-Qualification Questionnaire stage (PQQ)

 

Late July 12

 

Invite shortlist & competitive dialogue stage.  NB competitive dialogue stage continues until December 2012

 

Mid Dec 12

 

Receive written tenders

 

 

 

Late Feb 13

 

Appoint preferred bidder

 

TUPE information &consultation period

 

Mid March 13

 

Award contract

 

 

Early June 13

 

Start transition to new arrangements